Phutung substation

Installation, testing and commissioning of 132/11 kV GIS Phutung substation project with an installed capacity of two 45 MVA transformers, totaling 90 MVA. The substation is connected to the national grid by tapping the 132 kV double‑circuit transmission line extending from the Balaju–Chapali route.

Locationphutung
TechnologyGIS
Voltage / capacity132/11 kV · 2×45 MVA (90 MVA total)

Project overview

installation, testing and commissioning of 132/11 kV GIS Phutung substation project with an installed capacity of two 45 MVA transformers, totaling 90 MVA. The substation is connected to the national grid by tapping the 132 kV double‑circuit transmission line extending from the Balaju–Chapali route.